Deadlines

[25-Dec-20]#

  • create the UI in Next.JS and setup AntD and whatever is needed for the UI

[26-27-Dec-20]#

  • finish with the client data browser, and creating the zip file
  • work with Chonky see how uploads are to be implemented

[28-Dec-20]#

[29-Dec-20]#

  • setup EFS with all the dependencies
  • write the training code that will be executed by celery

[31-Dec-20]#

  • setup Docusarous

Lost Track#

  • At this point i was working so much that i had lost track of what i was doing, exams, internship, this project, i just did whatever i could as soon as my exams got over and finished up the frontend and backend